Sound Transit announces further delays to Federal Way Link, other extension projects

Sound Transit is working to redesign a part of the light rail route near South 259th Place due to unstable ground.

Sound Transit recently announced updates on several light rail projects including the Federal Way Link Extension route.

The organization is in the process of growing its regional light rail network from the current 26 miles to 62 miles of increased access and routes.

Federal Way Link Extension (FWLE) is one of five Sound Transit Link projects underway, along with the Hilltop Tacoma Link Extension, East Link Extension, Lynnwood Link Extension and Downtown Redmond Link Extension.

“We’re talking to the board right now about when they can open in a logical sequence that, again, can be done safely and with quality,” said Julie Timm, who took over as CEO of Sound Transit in September.

The Dec. 8 update notes several delays in the opening of these projects due to construction re-designs and engineering challenges — issues Timm says are being resolved.

“We’ve seen delays caused by the pandemic and its ongoing effects on the labor market and global supply chain, a regional concrete delivery strike, and design and construction quality issues on some projects,” according to Sound Transit’s Dec. 8 update.

In August this year, the organization discovered an unstable ground along the route adjacent to I-5 and South 259th Place in Kent, between the incoming Star Lake and Kent/Des Moines stations, causing a delay in construction.

Now, Sound Transit said it is redesigning a new long-span bridge over the area, but is still working to confirm a schedule with the contractor.

Project openings will take place in order of the completion of construction with the first being Lynnwood Link Extension first in summer or fall of 2024, followed by the East Link and Downtown Redmond extensions simultaneously in spring of 2025. The third project opening will be the Federal Way Link Extension, with an opening date not yet decided due to the contractor schedule discussions, according to Sound Transit.

Sound Transit had planned to open the Federal Way route in fall or winter of 2024 but that date has been pushed into 2025 at the earliest.

Sound Transit plans to preserve a window of at least six months between project openings. This block of time allows two months for staff to troubleshoot issues, address passenger needs and collect feedback on the service performance, according to the organization.

The additional four months “pre-revenue service” for operator and maintenance staff training and intensive testing to ensure all stations, tracks, signals and other infrastructure “work together as expected before we welcome new passengers to the opening of the next extension,” according to Sound Transit.

Along with construction and engineering challenges, hiring shortages of skilled labor, operator and maintenance workers may also delay project openings for Sound Transit.

“We need to double the current rate of hiring to meet the needs for our system, and this is a sector-wide and regionwide challenge,” according to Sound Transit. “If unaddressed, it could add up to six months to each project timeline.”

In January 2023, the Sound Transit Board of Directors will provide feedback on two scenarios for opening. The organization is considering the possibility of opening parts of the East Link Starter Line, a single extension route, to areas of Redmond Technology Station to South Bellevue before a project’s “full readiness.”

FINAL EIS

In December 2021, the board of directors identified the South 336th Street location as the preferred alternative for the incoming Operations and Maintenance Facility (OMF) South.

Identifying a preferred alternative is not a final decision, but instead gives an indication of the board’s preference based on information from draft reports and feedback.

The final Environmental Impact Statement (EIS) report, and the board’s Project to Be Built action, is expected to be published in spring 2023 at the earliest. The original plan was to have the report published by the end of this year.

In a November update, Sound Transit says design efforts have caused the delays.

The final EIS report will include input from local Tribes, members of the community and residents, various agencies and the City of Federal Way.

“After we issue the Final EIS, the Board will select the OMF South project to build,” according to Sound Transit.


Talk to us

Please share your story tips by emailing editor@kentreporter.com.

To share your opinion for publication, submit a letter through our website https://www.kentreporter.com/submit-letter/. Include your name, address and daytime phone number. (We’ll only publish your name and hometown.) Please keep letters to 300 words or less.

More in News

t
SeaTac man, 21, fatally shot in vehicle in Kent on West Hill

Someone ran up and fired multiple shots into vehicle Nov. 21 at Veterans Drive and Military Road

Kentwood High School, 25800 164th Ave. SE, in Covington, remained without power Thursday morning, Nov. 21, according to Puget Sound Energy. COURTESY PHOTO, Kent School District
Kent schools remain closed due to windstorm damage, power outages

Second consecutive day of closures Thursday, Nov. 21 across the Kent School District

t
Kent-based Puget Sound Fire calls windstorm ‘one for the ages’

Agency responds to 308 calls in 12-hour period, including 245 for storm-related issues

Crews clear trees from State Route 18, which the Washington State Patrol closed in both directions Wednesday, Nov. 20, from Issaquah Hobart to I-90 over Tiger Mountain because of fallen trees during a windstorm. COURTESY PHOTO, Washington State Patrol
Windstorm closes Kent schools, roads due to fallen trees

Many without power in areas of Kent and beyond

t
“Prolific” vehicular theft suspect arrested in Renton

Kent man holds 13 prior convictions and 41 arrests.

tt
Green Kent volunteer program wraps up season at city park

Volunteers remove invasive species, plant native trees and shrubs at Mill Creek Canyon Earthworks Park

t
Copper-wire thieves damage Kent Senior Center roof refrigeration unit

Facility temporarily loses commercial kitchen refrigerator but staff, community keep meals going

t
16-year-old girl dies in Covington single-car crash

Teen was driving when car crashed into a tree Nov. 15 along SE 256th Street just east of Kent

t
Kent Police Blotter: Oct. 24-Nov. 7

Incidents include carjacking, juvenile fight, stolen vehicle pursuit

t
State Patrol catches a pair of motorcycles going over 100 mph on I-5

See a video of their arrest. Agency uses air surveillance to pursue from Federal Way to Renton

Photos by Bailey Jo Josie/Sound Publishing
Official ribbon cutting for the Kent Valley Bezos Academy, which is still accepting applications for the 2024-2025 school year.
Kent Valley Bezos Academy offers student-driven preschool experience

New school offers free enrollment to children of income-eligible families

COURTESY PHOTO, King County
Driver reportedly going 111 mph in Kent fatal collision

SeaTac man, 33, faces vehicular homicide, reckless driving charges in Nov. 4 death of 38-year-old woman